The Web / Organizations / Oracle Cloud Infrastructure

Dossier · Organization

Oracle Cloud Infrastructure

verification: confirmed

The campus's confirmed tenant, which the record says funds all energy costs and hosts OpenAI workloads.

Conflicts of interest · 2

Flagged entanglements involving this party. Characterization on disclosed facts — see the full ledger and each party’s right of reply.

At a glance

Kind
Company
Role in the project
Tenant
Jurisdiction
Private sector (no public jurisdiction)
Public position
Publicly supports the project — Published a July 2026 announcement presenting the project as “$4.7 billion to New Mexico.”[3]
Verification
confirmed — Two independent accounts agree
In the record
3 sources · 19 connections · 24 dated entries
Record id
PJO1

Key facts

  • 2025-09-18Registered “Green Chile Ventures” as an alternate name of Oracle America Cloud Services LLC on September 18, 2025, the day before the county's bond vote.
  • 2026-04-27Published its “Project Jupiter Water Facts” statement on April 27, 2026.[1]
  • 2026-07-28Its July 28, 2026 presentation to the county built a $4.7 billion benefit figure that, by its own footnote, assumed the air permit and pipeline would be approved on time.
  • 2026-09-08Told commissioners on September 8, 2026 that it is contractually obligated to STACK for 17.9 years, against 30-year bonds, and that its intent is to renew.
  • 2026-09-16Registered a $3,444,500 lobbying advertising campaign, paid entirely to Brabender Cox, which the State Ethics Commission called the largest reported since 2021.
  • 2026-09-24Sent STACK Infrastructure a force majeure notice, reported September 24, 2026, pointing to delays in the air permit and the Green Chile pipeline; Oracle called such notices “commonplace.”

The record

tenant; funds all energy costs; hosts OpenAI workloads

Relationships · 19

In the timeline · 24

Sep 18, 2025Oracle's New Mexico entity registers — the day before the voteNov 12, 2025Every bond is bought by a company on the borrowing sideFeb 14, 2026The Senate passes the Microgrid Oversight Act, 22–20Feb 19, 2026The oversight bill dies at adjournmentApr 27, 2026Oracle publishes “Project Jupiter Water Facts”Jul 28, 2026“Long-term” means 17.9 years — and the $4.7 billion assumes the permit and pipelineAug 15, 2026The jobs report arrives — two weeks late, eight pages, signed by Oracle’s tax directorAug 25, 2026Oracle's fifteen-year water number, broken out at lastSep 8, 2026Oracle names a fallback, and the chair names the consequenceSep 8, 2026“Contractually, Oracle’s obligated to our provider STACK for 17.9”Sep 14, 2026The first general-election reports show the project’s moneySep 16, 2026Oracle discloses a $3,444,500 ad campaign for the permit — the largest ever reported in the stateSep 17, 2026The race for governor takes a position on data centers — two of themSep 21, 2026A million dollars for Gadsden’s schoolsSep 21, 2026The lobbyists, by nameSep 24, 2026Oracle sends a force majeure noticeSep 30, 2026Floodwater reaches the campusOct 8, 2026Oracle weighs trucking gas to the siteOct 13, 2026Three announcements, twenty minutes before the meetingOct 13–14, 2026After the comment window closes, the pipeline’s backers fileOct 14, 2026Three campuses, two states, one skyOct 15, 2026Oracle proposes a cap on the fuel cellsOct 27, 2026The county moves to notify the companies of a potential breachNov 10, 2026A second breach notice, over the jobs report

Dated entries in the record that involve this party. Appearing here is not an allegation — it means the graph draws an edge from this dossier to that event.

Claims involving them · 11

Oracle's own water numbers, on the recordprimary-source
Oracle's August 2026 water statement: 'nine single family homes'confirmed
Oracle's fifteen-year water total, broken out — and the two ways it is statedconfirmed
The developers have given more than $272,000 to New Mexico politicians this cyclecaveated
Seven lobbyists, five registered employers: who is paid to advance the project in Santa Feprimary-source
Oracle's contract runs 17.9 years; the tax break runs 30primary-source
Oracle's own $4.7 billion assumed the air permit and pipeline arrive on timeprimary-source
What the project's companies gave, in the state's own filings (2025–26)primary-source
The project's executives gave the Democratic nominee $112,200; the Republican, nothingprimary-source
Every Jupiter bond was bought by a company on the borrowing sideprimary-source
Oracle says its emissions will be lower than it applied for, and net zero by 2031confirmed

In the Watch · 19

eventOracle bondholder securities-fraud class action
promiseDaily water use comparable to a typical office building; a closed-loop, one-time fill; no public drinking water for cooling.
promise$6.9M community/workforce fund.
promise~92% NOx reduction versus the original gas-turbine plan (Bloom fuel cells).
eventWhite House Stargate announcement (Jan 21 2025)
eventAbilene 85% property-tax abatement approved (2025)
eventOracle files Taylor County property-value protest (2026)
eventOracle-OpenAI $300B contract signed (Sep 10 2025)
eventBloom fuel cell pivot (Apr 27 2026)
eventOracle NMED permit-support letter, signed Pitcock (Mar 2026)
eventBloom Q1 2026 first positive operating cash flow (~$73.6M)
documentOracle Congressional Fact Sheet (Sep 23 2025)
documentOracle 'Project Jupiter Water Facts' blog (Apr 27 2026)
documentEO 14318 — Accelerating Federal Permitting of Data Center Infrastructure
eventOracle issues an RFP for up to 2 GW of New Mexico renewables and funds carbon-capture research (Sept 8 2026)
documentOracle's 2026 Report of Advertising Campaign, filed with the Secretary of State (Sept 11 2026)
documentOracle's July 28 2026 presentation to the county commission
eventOracle proposes an output cap on the fuel cells (Oct 15 2026)
eventOracle's three announcements and the county meeting (Oct 13 2026)

Sources · 3

Contact us about this entry

Corrections, updates, and disputes are taken seriously and logged. If you are the subject of this page, this is your standing right of reply.

I am contacting…
Send via your mail app ↗

Opens your email client addressed to projectjupiterwatch@protonmail.com. Nothing is transmitted until you press send there. Responses from those named in the Watch are published verbatim.

Before New Mexico decides
No hearing date is set.

The decision was due July 21. Instead: a public hearing — first set for October, moved up to September 14 at the applicant’s request, stayed by the Supreme Court, reset for December 7, then vacated on November 6, after the applicant waived the department’s November 23 decision date. No new date will be set until the department files its revised recommendation. A $165B question for one desert county, on a schedule that keeps moving. The clock above always shows the next date that matters. Until the ruling, and after, this is the public watch on how it’s being made.

Take action →