The Web / Who's Who / Stephen Lopez

Dossier · Who's Who

Stephen Lopez

Assistant County Manager, Doña Ana County government (staff) · Joint acting county manager, Doña Ana County government (staff)
verification: confirmed

Doña Ana County's Assistant County Manager and operational spokesperson on the project, named one of three joint acting county managers in July 2026.

At a glance

Current roles
Category
Agency staff
Jurisdiction
Doña Ana County
Verification
confirmed — Two independent accounts agree
In the record
0 sources · 1 connections · 1 dated entries
Record id
PJP57

Key facts

  • Speaks for the county on the project's grading permits, site work and desalination.
  • 2026-07-28Appointed a joint acting county manager with Deb Weir and Lucio Luttrell on July 28, 2026, after the county manager's contract was terminated.

The record

Assistant County Manager; the county's operational spokesman on Jupiter (grading permits, site work, desalination)

Relationships · 1

In the timeline · 1

Jul 28, 2026The manager who signed the framework MOU is gone; three acting managers take over

Dated entries in the record that involve this party. Appearing here is not an allegation — it means the graph draws an edge from this dossier to that event.

Sources · pending

The sourcing pass for this entry is in progress. Nothing on this page is presented as beyond its verification tier until citations are attached.

Contact us about this entry

Corrections, updates, and disputes are taken seriously and logged. If you are the subject of this page, this is your standing right of reply.

I am contacting…
Send via your mail app ↗

Opens your email client addressed to projectjupiterwatch@protonmail.com. Nothing is transmitted until you press send there. Responses from those named in the Watch are published verbatim.

The hearing has passed
The Watch stands.

The decision was due July 21. Instead: a public hearing — first set for October, then moved up to September 14 at the applicant’s request — and a ruling due by November 23. A $165B question for one desert county, on a schedule that keeps moving. The clock above always shows the next date that matters. Until the ruling, and after, this is the public watch on how it’s being made.