Dossier · Organization

US Economic Development Administration (EDA)

verification: confirmed

The federal agency whose Quantum Tech Hub award is the data-center rationale stated in the state's MOU with BorderPlex.

At a glance

Kind
Government agency
Jurisdiction
Federal (U.S.)
Verification
confirmed — Two independent accounts agree
In the record
0 sources · 0 connections · 0 dated entries
Record id
PJO47

Key facts

  • 2024-07-02Awarded about $41 million to the Elevate Quantum Tech Hub, a Colorado–New Mexico consortium, on July 2, 2024, one of 12 Tech Hubs.

The record

EDA awarded ~$41M to the Elevate Quantum Tech Hub (CO-NM consortium) Jul 2 2024, one of 12 Tech Hubs. The MOU's stated data-center rationale

Sources · pending

The sourcing pass for this entry is in progress. Nothing on this page is presented as beyond its verification tier until citations are attached.

Contact us about this entry

Corrections, updates, and disputes are taken seriously and logged. If you are the subject of this page, this is your standing right of reply.

I am contacting…
Send via your mail app ↗

Opens your email client addressed to projectjupiterwatch@protonmail.com. Nothing is transmitted until you press send there. Responses from those named in the Watch are published verbatim.

The hearing has passed
The Watch stands.

The decision was due July 21. Instead: a public hearing — first set for October, then moved up to September 14 at the applicant’s request — and a ruling due by November 23. A $165B question for one desert county, on a schedule that keeps moving. The clock above always shows the next date that matters. Until the ruling, and after, this is the public watch on how it’s being made.