Dossier · Organization
Public Citizen
A national consumer-advocacy nonprofit that filed a FERC protest arguing the Green Chile pipeline application is incomplete.
At a glance
- Kind
- Nonprofit
- Key people
- Tyson Slocum
- Public position
- Publicly opposes the project — Filed a FERC protest asking that the Green Chile pipeline application be rejected as incomplete.[1]
- Verification
- confirmed — Two independent accounts agree
- In the record
- 1 sources · 1 connections · 0 dated entries
- Record id
- PJO105
Key facts
- 2026-04-13Protested the Green Chile pipeline at FERC in docket CP26-80, arguing the application must be rejected as incomplete.[1]
- Tyson Slocum is the staff member the record ties to the protest.
The record
The national watchdog that took the pipeline fight federal — its FERC protest argues the Green Chile application must be rejected as incomplete.
Relationships · 1
In the Watch · 1
Sources · 1