Skip to content
This site is continuously updated. Last updated:

Part of Project Jupiter Watch — the public record of the $165B data-center deal in Doña Ana County, NM. New here? Start with the Film →

The Web / Organizations / NM Public Regulation Commission (PRC)

Dossier · Organization

NM Public Regulation Commission (PRC)

verification: unverified

The state utility regulator whose rate and oversight authority the HB 93 carve-out removes for microgrids through 2035.

At a glance

Kind
Government agency
Jurisdiction
State of New Mexico
Verification
unverified
In the record
0 sources · 0 connections · 1 dated entries
Record id
PJO59

Key facts

  • 2026-02-14The Microgrid Oversight Act, which would have put the commission over microgrids, passed the Senate 22–20 on February 14, 2026 and died in the House.
  • Reviews El Paso Electric's 2026–2035 expansion plan.

The record

Rate/oversight authority the HB 93 carve-out exempts microgrids from (to 2035); SB 235 would restore oversight

In the timeline · 1

Mar 20, 2025The amendment: Section 6 is added to HB 93; the Senate passes it 37–4

Dated entries in the record that involve this party. Appearing here is not an allegation — it means the graph draws an edge from this dossier to that event.

In the Watch · 1

eventEPE 2026-2035 Expansion Plan / $308M resiliency (Dec 2025)

Sources · pending

The sourcing pass for this entry is in progress. Nothing on this page is presented as beyond its verification tier until citations are attached.

Contact us about this entry

Corrections, updates, and disputes are taken seriously and logged. If you are the subject of this page, this is your standing right of reply.

I am contacting…
Send via your mail app ↗

Opens your email client addressed to projectjupiterwatch@protonmail.com. Nothing is transmitted until you press send there. Responses from those named in the Watch are published verbatim.

The hearing has passed
The Watch stands.

The decision was due July 21. Instead: a public hearing — first set for October, then moved up to September 14 at the applicant’s request — and a ruling due by November 23. A $165B question for one desert county, on a schedule that keeps moving. The clock above always shows the next date that matters. Until the ruling, and after, this is the public watch on how it’s being made.