The Web / Organizations / Environmental coalition (CBD / Sierra Club / Food & Water Watch)

Dossier · Organization

Environmental coalition (CBD / Sierra Club / Food & Water Watch)

verification: unverified

A coalition of the Center for Biological Diversity, Sierra Club and Food & Water Watch that has protested the Green Chile pipeline and challenged the campus's emergency well.

At a glance

Kind
Community group or coalition
Role in the project
Intervenor or party to a proceeding · Litigant
Verification
unverified
In the record
0 sources · 2 connections · 4 dated entries
Record id
PJO19

Key facts

  • 2026-04-15Filed protests at FERC against the Green Chile pipeline on April 15, 2026.
  • 2026-01-09The Center for Biological Diversity filed its protest of the emergency-well application on the January 9, 2026 deadline, one of 32 protests on file.
  • 2026-08-20The Center's 151-page mandamus petition of August 20, 2026 cited the State Engineer's meter record: 103,620,944 gallons drawn from the new well between April 14 and July 31, 2026.
  • 2026-09-17The Supreme Court stayed the emergency-well authorization on August 23, 2026, then denied the petition and lifted the stay on September 17, 2026.

The record

Filed FERC protests against the Green Chile pipeline

Relationships · 2

Counts as member· 2

In the timeline · 4

Claims involving them · 3

More than 103 million gallons have been pumped from the emergency well since April 2026confirmed
CBD argues the October 2025 authorization required advertisement and a hearing that never happenedcaveated
A protest filed on the deadline sat seven months without a docketed hearing while the well pumpedprimary-source

In the Watch · 2

eventEnvironmental groups protest at FERC (Apr 15 2026)
eventNM Supreme Court stays the emergency well authorization (Aug 23 2026)

Sources · pending

The sourcing pass for this entry is in progress. Nothing on this page is presented as beyond its verification tier until citations are attached.

Contact us about this entry

Corrections, updates, and disputes are taken seriously and logged. If you are the subject of this page, this is your standing right of reply.

I am contacting…
Send via your mail app ↗

Opens your email client addressed to projectjupiterwatch@protonmail.com. Nothing is transmitted until you press send there. Responses from those named in the Watch are published verbatim.

The hearing has passed
The Watch stands.

The decision was due July 21. Instead: a public hearing — first set for October, then moved up to September 14 at the applicant’s request — and a ruling due by November 23. A $165B question for one desert county, on a schedule that keeps moving. The clock above always shows the next date that matters. Until the ruling, and after, this is the public watch on how it’s being made.